home

Basement sub-floor

December 7th, 2008

To do the basement sub-floor, I’m using a product called Delta-FL, which I picked up at Rona. It’s basically a big roll of dimpled plastic, which sits on top of the basement slab and acts as a vapour barrier, adds an air gap that helps insulate the floor, and also raises the floor up off the ground to avoid water damage in case there is a tiny amount of water. On top of this, I’m putting 5/8″ OSB, and then using tap-cons to secure the OSB to the floor. Although you can put some flooring (eg, laminate) directly on top of the Delta-FL, I was a bit worried about doing that since there are a couple places that aren’t totally level - the OSB lets me even them out and get very close to perfectly level.

Once very nice thing about this flooring system is the minimal height it requires. Since my basement is a bit short (7′ 3″ unfinished floor to joists, 6′ 6″ unfinished floor to heating ducts), I wanted to keep as much of that as possible. The total height is just over 1″, so it really isn’t bad.

I have a 12″ piece of vapour barrier plastic underneath all the exterior framed walls. I called the manufacturer of Delta-FL to check what the best way of dealing with that was, and they advised me to tape the barrier directly to the Delta-FL, forming basically a complete seal around the walls. I used tuck tape to do this, and tape all the pieces together. I had to cut a couple holes out to fit the floor drain, toilet drain, and a jack post in the middle of the basement.

I worked in sections, putting a couple strips of Delta-FL down, and then laying the OSB on top of it, and connecting the grooves up. Once I had a couple pieces of OSB down, I would take some tap-cons and secure down the first row - I found it was much harder to get the tongue and groves of the OSB to connect up, if one of the pieces was already screwed down. I left 1/8″ gap between all the pieces of OSB, and the exterior framing. I was also careful to stagger all the sheets of OSB, so all of the ends are offset, forming stronger joints.

For the floor drain, I just made some careful measurements and then used my jigsaw to cut out a hole.

The toilet drain happened to line up with the edge of a piece of OSB, which made cutting the hole much easier. As you can see above, I also made sure the jack post was on an edge, so I only had to cut a U shape out of one piece - the other just butts up against the edge.

Though I don’t plan on doing anything with the crawlspace floor, I did put the sub-floor into the door opening, to make it easier to put the door on, as well as to hide the edge of the floor from the finished basement.

Today it is -10° Celsius out, and the surface temperature of the unfinished floor in the crawlspace is 9°, while the surface temperature of the OSB is 14°. The basement walls are still uninsulated, so this may not be overly conclusive, but it does show that it makes a difference.

Update: My girlfriend says “the basement floor feels much warmer now”. I guess that’s conclusive.

Upgrading electical panel

December 2nd, 2008

The house was built in 1975, so there are two implications as far as electrical goes: there is aluminum wiring, and there is a fuse box.

Not too much I can do about the aluminum, and in fact, so long as it’s done properly, aluminum is quite safe. It’s still often used for service entrance wiring (eg, from the pole to your panel), and it’s still used extensively throughout the electricity distribution system. The only real problem happens when you connect devices (switches, receptacles) that aren’t rated for aluminum. There are special wire connectors to use (#63) when connecting aluminum wires, so that is something else to pay attention to.

As far as the fuse panel, there were a few reasons I wanted to replace it, even though it wasn’t absolutely essential. I wanted to insulate behind it, and it was mounted on a piece of plywood, directly on the cement wall. This meant that I’d have to completely take it off anyways to insulate, or just deal with a big uninsulated portion of the wall (seemed dumb, when I’m putting a lot of effort into insulating). I also don’t really like working with old boxes, and I do need to add a few circuits. Thought I had some space to expand, starting from scratch is easier. There is also the convenience factor, as breakers are simple easier to deal with than fuses.

I had an electrician do the upgrade, since to move the panel out from the wall, the wires coming from the meter needed to be extended a few inches. I didn’t really want to do that myself, or have to deal with Hydro One and the inspectors, so it was just simpler to pay someone else to do it.

Before the electrician showed up, I framed around the panel, and built a piece that would fit in easily.

If you look closely in the first picture below, you can see the gray conduit sticking out of the header, which goes directly to the gray pull box on the outside of the house in the next picture.

I put in the framing, and filled it with fiberglass insulation, 1 1/2 pieces thick, so it should be rated about R-20. A few hours after installation, I took some temperature readings: the outside temperature was ~1° Celsius; the cement wall right beside the panel was ~2° Celsius; and the plywood the panel is mounted on was ~18° Celsius.

Tear-down and framing exterior walls

November 30th, 2008

I’m going to be putting in closed-cell spray foam insulation. The big advantage here is the minimal space required - 3″ is over R-20, and it can fit in a 2×4 framed wall.

To start with , here’s a couple shots of what I ripped out.

Half of the basement had some old insulation that had an R-value of maybe R-7. It also had an integrated paper vapour barrier, which is not very effective. Not that it really mattered, the other half of the basement had no insulation at all, as you can see here.

I took out all the old insulation, and disassembled the framing, which was made of 2×3’s with 1×2s in a grid pattern. This took an amazingly long time to take apart, since it was comprised of so many separate pieces of wood.

I left a ~1″ gap between the new framing and the cement wall, which will get filled with insulation. This minimizes the amount of heat transferred through the studs themselves. All the walls are anchored into the ground with concrete nails and/or tapcons, and anchored to the joists above using extra sections. I had to leave a gap at the top of some of the walls to allow access to the headers for spraying insulation, but it’s high enough that when I put the suspended ceiling in, it will not be visible.

There were a couple of annoyances during this process. The hot water heater was only about 2″ away from the cement wall. This meant I couldn’t frame or insulate behind it, which of course would be bad. I cut the pipes above it, drained it about half way, and moved it over so it’s now about 5″ from the wall. I also moved it back towards the furnace more, which allows me to move a 5′ wall about 6″ back in the laundry room.

Luckily, the tank is connected via a flexible copper gas line, so I was able to safely move it by myself. Note that I did turn the gas off to this line just to be safe.


I also noticed that the furnace filter was on the back of the furnace, where I was going to be putting a wall. I didn’t really want to put a dumb-looking access door on the wall, so I figured I’d give turning it around a shot. I was able to pull the return vent off, and then remove a couple of screws inside and turn the filter housing around. It now is accessible from the front of the furnace, which will be inside a utility closet in the laundry room.


I also put framing up in the crawlspace, so that if I want to put shelves up or whatever, it will be easy. Once the insulation is on the walls, it’s hard to build anything in front of it, since the surface is fairly uneven. Having the framing up now gives a nice flat surface to work with later. While most of the basement is 16″ studs, the crawlspace is 24″, which makes it a bit cheaper to build. Since it’s only a 4′ high wall, there probably won’t be any reduction in the strength of the drywall, not that it needs it there anyways.